September 24, 2007
To The Editor
The Cambridge Chronicle
Dear Sir:
I have been wondering for a couple of years now when the new park
in East Cambridge on the Charles
at North Point will finally open. I am
not talking about the North Point development project, which is
located on the other side of the Gilmore Bridge in the old B &
M rail
yards. You may have seen the park to your left as you go into
Boston on the OÕBrien Highway or
from the Green Line going across the
viaduct between Lechmere and SciencePark stations. If not you
should go and take a look.
Downriver from the Dam and viaduct, located on the old Federal Distillers site, you will see a beautiful
thing. This new park, five or so
acres in size, has two islands, four bridges, paths, fields,
really nice plantings, and a playground. You will also see that it is surrounded by a big
chain link fence decorated with a
lovely selection of no trespassing signs.
I live in East Cambridge and walk into Boston several times each
week to work in Haymarket Square.
While dodging traffic and duck boats
going in and out of the Museum of Science driveways, I get a view
of this park. It has looked just
days away from opening for over two
years. In fact in the summer of 2005 there was a sign on one of the gates announcing its opening in the
summer of 2004! That was my first clue that things were not going
well.
Last week, I couldnÕt take it any more so I started some
inquiries. I
e-mailed the members of the City Council and the Cambridge Chronicle asking if they knew anything and could
do some investigating and advocating
about these delays. Councilor Davis replied ÒI will look into this.Ó Councilor Maher replied, ÒI
have submitted a Council order for
MondayÕs meeting regarding your concerns.Ó Councilor (and State Rep.) Toomey, to his credit,
responded with actual knowledge of
the issue and related that he recently met with project representatives on the site and was
given some explanation and assurance
that he will try to get an update. The Chronicle said that they would look into it and suggested
writing a letter to the editor, ergo.
I also called Mass. DCR, which I assumed to be the
responsible
agency. The next day I got a call back from someone there who told
me that while upon completion the
park is to be turned over to DCR, it
is a Big Dig project. At that point, all of this made a bit more sense. I still wasnÕt ready to give up,
though, so I searched the Mass.
Turnpike AuthorityÕs Big Dig website for contact information and found a form to e-mail questions
and comments. I sent in some and was
not expecting to get any further there based on their reputation for accountability. However, a couple
of days later, I got a call. Unfortunately
I wasnÕt able to take notes at the time, but wrote the gist of it down later that night.
I spoke with Fred Yalouris whose job title has architecture
and
engineering in it, but I donÕt remember it precisely. In my e-
mail,
I asked several questions about what is still to be done and what
the holdups are. Here is what I
was told.
1. When construction began the site was found to be contaminated
with asbestos. This had to be
cleaned up before park construction began
and took a long time. However park construction began in 2002 or
2003 as I recall
2. Most of the trees need to be replaced. During the recent
dry
weather, they were allowed to dry up and die.
3. The granite edgestones were not manufactured to specifications
and had to be sent back to the
contractor for reworking and or
replacement. As far as I can tell, this has been done for some
time now.
4. The coating (high tech paint) on the railings along the
riverbank
ÒfailedÓ, as in cracked and peeled. Some three hundred sections
of
this had to be sent back to the contractor for sandblasting and
re-
coating. They have not come up with a temporary solution and
several sections are still
missing.
5. When the park is turned over to the DCR, all obligations on
the
part of these contractors ends and all costs and liabilities
will
fall to DCR. DCR doesnÕt want any part of it until everything is fixed.
6. Mr. Yalouris said he thought that the park would open in mid
to
late October.
Forgive me if IÕm skeptical, but my daughter who was six when
we
started looking forward to playing in this park is about to turn
ten.
I hope she hasnÕt grown up and moved away by the time it happens.
With this degree of monitoring and oversight, one has to be
thankful that more people havenÕt
died as a result of shoddy materials and
workmanship on the Big Dig. However, as we have recently seen in
the Turnpike AuthorityÕs decision
to reverse the monumentally stupid
decision not to open the Mass Pike U-turn lane at the Allston exit until after the toll hike, maybe the
can be persuaded to put some real
pressure on these guys and get it done. Mr. Yalouris gave me his phone number at MTA and said to call if
I have any further concerns.
My biggest concern is that he will think that IÕm the only one
that
really cares, and therefore he wonÕt really have to worry about
it.
So PLEASE call him. His number is 617 951-6015. He is a
public
employee, we pay his salary, donÕt be afraid to let him know that
you care. Call your city
councilors (it is an election year) and state
rep. and senator too.
Thank you,
Mark Jaquith
Hurley Street