September 24, 2007

To The Editor

The Cambridge Chronicle

 

 

Dear Sir:

I have been wondering for a couple of years now when the new park in  East Cambridge on the Charles at North Point will finally open. I am  not talking about the North Point development project, which is 

located on the other side of the Gilmore Bridge in the old B & M rail 

yards. You may have seen the park to your left as you go into Boston  on the OÕBrien Highway or from the Green Line going across the  viaduct between Lechmere and SciencePark stations. If not you should  go and take a look. Downriver from the Dam and viaduct, located on  the old Federal Distillers site, you will see a beautiful thing. This  new park, five or so acres in size, has two islands, four bridges,  paths, fields,  really nice plantings, and a playground. You will  also see that it is surrounded by a big chain link fence decorated  with a lovely selection of no trespassing signs.

 

I live in East Cambridge and walk into Boston several times each week  to work in Haymarket Square. While dodging traffic and duck boats  going in and out of the Museum of Science driveways, I get a view of  this park. It has looked just days away from opening for over two  years. In fact in the summer of 2005 there was a sign on one of the  gates announcing its opening in the summer of 2004!  That was my  first clue that things were not going well.

 

Last week, I couldnÕt take it any more so I started some inquiries. I 

e-mailed the members of the City Council and the Cambridge Chronicle  asking if they knew anything and could do some investigating and  advocating about these delays. Councilor Davis replied ÒI will look  into this.Ó Councilor Maher replied, ÒI have submitted a Council  order for MondayÕs meeting regarding your concerns.Ó Councilor (and  State Rep.) Toomey, to his credit, responded with actual knowledge of  the issue and related that he recently met with project  representatives on the site and was given some explanation and  assurance that he will try to get an update. The Chronicle said that  they would look into it and suggested writing a letter to the editor,  ergo.

 

I also called Mass. DCR, which I assumed to be the responsible 

agency. The next day I got a call back from someone there who told me  that while upon completion the park is to be turned over to DCR, it  is a Big Dig project. At that point, all of this made a bit more  sense. I still wasnÕt ready to give up, though, so I searched the  Mass. Turnpike AuthorityÕs Big Dig website for contact information  and found a form to e-mail questions and comments. I sent in some and  was not expecting to get any further there based on their reputation  for accountability. However, a couple of days later, I got a call.  Unfortunately I wasnÕt able to take notes at the time, but wrote the  gist of it down later that night.

 

I spoke with Fred Yalouris whose job title has architecture and 

engineering in it, but I donÕt remember it precisely. In my e- mail, 

I asked several questions about what is still to be done and what the  holdups are. Here is what I was told.

 

1. When construction began the site was found to be contaminated with  asbestos. This had to be cleaned up before park construction began  and took a long time. However park construction began in 2002 or 2003  as I recall

 

2. Most of the trees need to be replaced. During the recent dry 

weather, they were allowed to dry up and die.

 

3. The granite edgestones were not manufactured to specifications and  had to be sent back to the contractor for reworking and or 

replacement. As far as I can tell, this has been done for some time now.

 

4. The coating (high tech paint) on the railings along the riverbank 

ÒfailedÓ, as in cracked and peeled. Some three hundred sections of 

this had to be sent back to the contractor for sandblasting and re-

coating. They have not come up with a temporary solution and several  sections are still missing.

 

5. When the park is turned over to the DCR, all obligations on the 

part of these contractors ends and all costs and liabilities will 

fall to DCR. DCR doesnÕt want any part of  it until everything is fixed.

 

6. Mr. Yalouris said he thought that the park would open in mid to 

late October.

 

Forgive me if IÕm skeptical, but my daughter who was six when we 

started looking forward to playing in this park is about to turn ten. 

I hope she hasnÕt grown up and moved away by the time it happens. 

With this degree of monitoring and oversight, one has to be thankful  that more people havenÕt died as a result of shoddy materials and  workmanship on the Big Dig. However, as we have recently seen in the  Turnpike AuthorityÕs decision to reverse the monumentally stupid  decision not to open the Mass Pike U-turn lane at the Allston exit  until after the toll hike, maybe the can be persuaded to put some  real pressure on these guys and get it done. Mr. Yalouris gave me his  phone number at MTA and said to call if I have any further concerns. 

My biggest concern is that he will think that IÕm the only one that 

really cares, and therefore he wonÕt really have to worry about it. 

So PLEASE call him. His number is 617 951-6015. He is a public 

employee, we pay his salary, donÕt be afraid to let him know that you  care. Call your city councilors (it is an election year) and state 

rep. and senator too.

 

Thank you,

Mark Jaquith

Hurley Street